Indirect costs in construction
Indirect costs (or indirect spend) are those costs that are necessary to keep a process or project running, but which do not vary directly with the volume of goods or services produced and are not easily attributable to a particular process or project. This might for example include; rent, insurance, advertising and marketing and so on. These types of indirect costs may be referred to as overheads.
This is as opposed to direct costs, which are those costs incurred directly by production and include items such as raw materials, labour, equipment, power and so on. Direct costs can be traced and are attributed to a cost ‘object’ which may be a product, department, cost centre or project.
So, indirect costs do not vary directly with production levels, whereas direct costs remain dependent on production levels and will vary when production is increased or decreased.
NB Cost prediction, Professional Statement, 1st edition, published in November 2020 by the Royal Institution of Chartered Surveyors (RICS), defines indirect costs as: ‘…costs incurred during construction works that cannot be attributed to any one section of the works; they may be fixed (e.g. the cost of bringing accommodation to the site) or time-related (e.g. the cost of insurance or security personnel).’
For more information see: Direct costs.
[edit] Related articles on Designing Buildings
Featured articles and news
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building 2024 judges choice winner
Once Upon a Pass by Liam Man.
CIOB Art of Building 2024 public choice winner
Fresco School by Roman Robroek.
HE expands finance alliance to boost SME house building
Project follows on from Habiko public-private place making pension partnership for affordable housing delivery.
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
How orchards can influence planning and development.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
I would like to know if prelim, overheads and profits are considered as "indirect costs"
They are typically considered to be indirect costs.