Indirect costs in construction
Indirect costs (or indirect spend) are those costs that are necessary to keep a process or project running, but which do not vary directly with the volume of goods or services produced and are not easily attributable to a particular process or project. This might for example include; rent, insurance, advertising and marketing and so on. These types of indirect costs may be referred to as overheads.
This is as opposed to direct costs, which are those costs incurred directly by production and include items such as raw materials, labour, equipment, power and so on. Direct costs can be traced and are attributed to a cost ‘object’ which may be a product, department, cost centre or project.
So, indirect costs do not vary directly with production levels, whereas direct costs remain dependent on production levels and will vary when production is increased or decreased.
NB Cost prediction, Professional Statement, 1st edition, published in November 2020 by the Royal Institution of Chartered Surveyors (RICS), defines indirect costs as: ‘…costs incurred during construction works that cannot be attributed to any one section of the works; they may be fixed (e.g. the cost of bringing accommodation to the site) or time-related (e.g. the cost of insurance or security personnel).’
For more information see: Direct costs.
[edit] Related articles on Designing Buildings
Featured articles and news
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
I would like to know if prelim, overheads and profits are considered as "indirect costs"
They are typically considered to be indirect costs.